CAP in the Camargo mexican photovoltaic plant

The provisional reception of the Camargo plant in Mexico has already been signed and the work of GRS O&M has begun.

GRS has achieved, within the expected period, the CAP of the Camargo project in Mexico by its client Balam Fund. The execution has been carried out in 11 months until the COD and has included the construction of the photovoltaic plant of 35.46 MWp and the works of interconnection and substation to connect to the grid.

From this moment, work begins to be carried out by the GRS O&M team, which includes all preventive and corrective maintenance work, with spare parts management, monitoring every day of the year and guarantee of availability .